‘Sberbank City’ at 32 Kutuzovsky Prospekt grew out of the Mirax Plaza project. Two unfinished towers were adapted to serve as Sber’s headquarters and linked by a glass entrance building. Its saddle-shaped roof accommodates a shared hall beneath it and reduces shading of the offices on the towers’ lower floors — allowing the architects to meet two of the new client’s requirements with a single form.
The story of the two towers and the entrance between them spans the original design of 2006–2007, the purchase of the complex in 2018 and the completion of the headquarters in summer 2021. Other buildings in the business district were developed separately, each to its own schedule.
What was the original design for Mirax Plaza?
In the Mirax Plaza design, two high-rise towers formed the core of a large complex near the junction of Kutuzovsky Prospekt, Kulneva Street and the Third Ring Road. An entrance lobby was already planned between them, but the glass building constructed later is much larger and has a different shape.
The architectural practice Sergey Kiselev & Partners lists Mirax Plaza among its non-residential projects in Moscow from 2006–2010. Reports on the purchase of the complex in 2018 describe the towers as having 47 and 41 storeys and still being unfinished. The high-rise silhouette therefore predated Sber’s final brief: the new owner worked with an existing building form rather than designing the towers from scratch.
The names associated with this site are easy to confuse. Engineering company Elevel’s project page records both Mirax Plaza and Suvorov Plaza in the site’s history, while reports on the deal separately mention the President Plaza building, which the bank was already using. These names refer to different phases and parts of the large site; it would be incorrect to assign the same acquisition date to every building indiscriminately.
A Mirax Plaza tower under construction and former factory buildings beside the Moskva River. 5 July 2015. Wikimedia Commons, Moscow, construction of Mirax Plaza and the former Kazakov Plant (395).jpg, author: karel291, licence: CC BY 3.0 source, license
Why did the original design take this form?
The twin towers of Mirax Plaza cannot be explained solely by a desire to create a prominent landmark. An analysis of the project published in 2008 entitled ‘Towers at the Crossroads’ sets out the site’s constraints: the metro, a railway and a pressurised sewer run nearby, while the ground slopes down towards the river by approximately ten metres. The architects had to accommodate an extensive brief on a site with complex boundaries and existing buildings that were to be retained. Building upwards was one way to fit the required floor space onto the site.
The site required the new development to be fitted around the existing buildings. According to the 2008 project analysis, the local police department building had to be demolished and rebuilt, while the neighbouring President-Service building was to be retained: the complex’s low-rise blocks were to wrap around it on three sides. The original composition was therefore shaped not only by the desired amount of office space and views from the main roads, but also by specific obstacles within the site.
The same the 2008 analysis presents Sergey Kiselev’s view on transport access for the project: a vehicle entrance could not be provided directly from the junction, the Third Ring Road or Kutuzovsky Prospekt. The original scheme envisaged access via 1812 Goda Street. This is a detail from the early design process, rather than directions for drivers in 2026. It shows why a site visible from several major roads required a separate solution for pedestrian and vehicle access.
The architects at Sergei Kiselev’s practice designed the towers with different numbers of storeys: 47 and 41. Their inward-facing surfaces are curved and glazed; in the original description, the outward-facing façades were divided by horizontal bands of stone. At the top, the towers were cut back towards Kutuzovsky Prospekt. These features belong to the original composition, so it would be incorrect to credit the entire present-day silhouette to the practice that later designed the glass entrance.
The two towers were only part of the vision. The scheme developed in the 2000s included lower buildings along Kutuzovsky Prospekt and the Third Ring Road, linked by a shared podium. The 2008 article describes lofty atriums in the lower buildings, offices on the main floors of the towers and apartments at the top. The original mix of uses is important to the history of the redevelopment: Sber’s commission changed how the spaces were used and how the buildings were connected, although the overall composition of the site was retained. The 2008 publication describes plans, rather than listing what had already been built by then.
The Mirax Plaza construction site viewed from Kulneva Street, 26 April 2016. Wikimedia Commons, Moscow, Kulneva Street, construction of Mirax Plaza (31212865055).jpg, author: Gennady Grachev from Moscow, Russia, licence: CC BY 2.0 source, license
In the early design, light also played a prominent role in the lower buildings. The 2008 analysis of the project describes four ten-storey atriums with glazed façades facing the street. Glass walls supported by steel cables and roofs formed from triangular rooflights were proposed for them. These are the atriums of the side buildings, rather than a description of the present-day space between the towers. Their presence in the drawings shows the architects’ sustained interest in light-filled communal spaces, but provides no grounds for regarding the current saddle-shaped entrance as a realisation of the same structure.
The glazed link is a particularly telling feature. Drawing on the original project drawings, a 2022 architectural review notes that an entrance lobby between the towers was envisaged as early as 2007. The later structure developed this idea: it grew longer and taller, acquired double curvature and filled the space between the buildings. The present-day building can therefore be described neither as an exact realisation of the Mirax Plaza drawings nor as an idea that emerged entirely from scratch.
Why were the other buildings designed by different architects?
The planned mix of uses at Mirax Plaza was changing even before Sberbank decided to consolidate its headquarters here. In April 2014, the Moscow Architectural Council discussed four design options for one of the remaining buildings. The report on the meeting links the redesign of the site to constraints imposed by the railway corridor: the original building layout encroached on railway land, and the architects were seeking a new way to accommodate the required floor space. The discussions concerned layout proposals, rather than buildings that had already been constructed.
According to a report by Archi.ru, changes to the project boundaries alongside the railway tracks almost halved the site area available for the low-rise building. The client transferred the commission from Sergei Kiselev’s practice to Roman Kananin’s practice and brought in Vladimir Plotkin’s TPO Reserve to develop an alternative design. Four options were discussed on 9 April 2014. The change of architects therefore concerned this building, rather than the two towers whose designs had already been prepared.
The cylindrical Mirax Plaza building viewed from Kutuzovsky Prospekt. Wikimedia Commons, Kutuzovsky Prospect 32 — Mirax-Plaza cylinder (31212864275).jpg, author: Gennady Grachev from Moscow, Russia, licence: CC BY 2.0 source, license
A single timeline helps clarify the difference between the original vision and the outcome: in 2006–2007, Sergei Kiselev’s practice developed the original architectural composition; in 2014, alterations to a separate low-rise building were discussed; in 2018, Sber announced the purchase of the unfinished buildings; and in 2020–2021, a new entrance design and the final interiors of the towers took shape. None of these milestones, taken on its own, marks the completion of the entire development.
Why did the unfinished complex become the bank’s headquarters?
Sberbank’s decision was driven by plans to bring together departments previously based at different addresses. In November 2018, Sber announced an agreement to purchase an office complex on Kulneva Street covering more than 300,000 square metres. According to the bank, the new site, together with the neighbouring buildings already in use, was intended to bring together more than 23,000 employees; at the time of the announcement, they were working in more than 40 offices across Moscow.
The figures in the documents refer to different project boundaries. A 2008 publication about Mirax Plaza gave an area of more than 368,000 square metres for the proposed complex; the bank’s 2018 announcement refers to the purchase of three buildings with a combined area of more than 300,000 square metres; in a 2022 Sber publication the figure given for the entire business cluster is already 600,000 square metres. These are not three estimates for a single completed building: the buildings included, the stage of construction and the scope of the calculation all changed. Comparing the areas without these qualifications would create an apparent contradiction.
In its 2018 announcement, the bank stated two practical aims for consolidating its offices: to reduce staff travel between buildings and to lower operating costs. These were planned benefits; the publication does not establish the actual savings achieved after the move.
The client’s representative Vasily Chekanov uses the OfficeNext project profile to define the original problem more precisely: the two freestanding towers had two separate entrances, while the space between them did not provide a unified point of arrival for the headquarters. This explains the addition of a central lobby and a large covered hall. Meetings with partners could be held in the reception area without sending every visitor up to the office floors. This separation of circulation flows follows from the layout described, rather than from any assumption that the entire complex is freely accessible.
The Sberbank City towers beyond the snow-covered Moskva River. Moscow, February 2026. Wikimedia Commons, Moscow Sberbank City 2026-02-17 7405.jpg, author: Mike1979 Russia, licence: CC BY-SA 3.0 source, license
The bank's statements in 2018 described a relocation plan, rather than the completed state of the entire site. Later reports from those involved provide a more accurate basis for assessing the outcome: Sber dates the completion of construction and reconstruction work on the two towers, with an entrance between them, to summer 2021. This date cannot automatically be applied to each subsequent building in the development.
What had already been done for Sber on this site?
Before the two towers were completed, Sber had already tried out a different type of office on Kutuzovsky Prospekt. According to Evolution Design's page on Building E, its interior design project was completed in December 2017. Spaces originally divided into residential units were adapted for flexible teams: workstations were placed by the windows, with communal areas and meeting rooms in the centre of the floor. This experience helps explain why daylight and a variety of layouts later received such close attention in the towers.
In Building E, the practice divided each floor into four functional zones around a shared central area with a meeting room, a library for quiet work and two kitchens. Between the workstations by the windows and the main circulation route, the architects placed small individual rooms: these provide a buffer against passing foot traffic and are suitable for calls or brief meetings. The same approach to planning later appeared in the towers' interiors, although the buildings themselves differ in scale.
An open-plan workspace in the Sbergile office on the 11th floor in 2018. Wikimedia Commons, Sbergile interior, 11th floor.jpg, author: Niklem, licence: CC BY-SA 4.0 source, license
Another stage was Building G, completed, according to the architects , in September 2019. A diamond-shaped meeting room is suspended in the internal atrium of this ten-storey building, connected to the sixth floor by a glass bridge. It belongs to Building G and is outside the space beneath the saddle-shaped roof between the two towers.
What did the architects add between the towers?
Between the towers, they built a separate three-level entrance building beneath a glass roof. According to the practice Evolution Design, the commission for an impressive shared entrance came in 2020. The design enclosed the previously open space and linked the two towers through a central reception hub, meeting areas and everyday amenities.
The architectural practice Evolution Design shaped the roof as a hyperbolic paraboloid: it rises towards both entrances and dips in the middle, resembling a saddle. This provides the height needed for a large hall at either end, while the central section casts less shade on the towers’ lower office floors.
The client’s brief called for an entrance serving around ten thousand employees in the two towers, a reception desk, restaurants, a conference centre and an amphitheatre, all under one roof. According to Evolution Design, this also had to preserve daylight for the offices on the lower floors of the two buildings.
How does the roof’s height vary?
The variation in height beneath the glass roof can be expressed in figures. A technical analysis of the glazing, prepared with input from supplier AGC, gives the height as approximately 20 metres in the central section and 28 metres at the entrances. These measurements refer to the interior of the covered space, rather than the dimensions of the towers. The rise towards the ends makes both entrances prominent; the lower central section helps preserve more daylight for the lower office floors.
The glass roof is not made from a single curved pane. According to the supplier, its surface is assembled from triangular units of varying sizes, which together create a double curvature. This gives physical form to the geometric term ‘hyperbolic paraboloid’: the architect’s complex line is translated into a grid of individual elements that can be manufactured and installed on site.
Sberbank City viewed from the street, 18 October 2024. Wikimedia Commons, Sberbank City 02.jpg, author: mos.ru, licence: CC BY 4.0 source, license
Why do the glass and metal portals work well together?
The glass roof admits daylight into the shared hall, while two steel portals mark the entrances at opposite ends of the building. Both components were designed around the same complex geometry: the curved surface had to be divided into individual elements, which were then manufactured and assembled between the existing towers.
At either end of the structure, Evolution Design installed outward-tilting triangular panels of champagne-coloured stainless steel. On the project page the practice explains how they relate to the finishes of other buildings on the campus. According to the designers, the polished steel reflects passers-by and appears to change hue as the daylight varies; this effect is visible at both entrances. As a result, the portals read as part of the wider ensemble, although their sculptural forms differ markedly from the rectilinear towers. This is the designers’ interpretation, rather than evidence that all the buildings were constructed at the same time.
Inside, the form is supported by a system of curved steel arches described in the OfficeNext project profile. It also names those involved in delivering the project: Evolution Design, in partnership with ATP TLP, was responsible for the architectural design, MOST for the structural design and construction, and Struktura for the entrance portals. This division of responsibilities is worth remembering when the entire visible result is attributed to a single practice: the concept, engineering design and installation were distinct areas of work here.
The sources give different floor areas for the entrance building. Evolution Design cites a net floor area of 6885 square metres, while the OfficeNext project dossier gives a gross floor area of 9550 square metres. These figures describe different measures, so they should neither be added together nor should the difference be presented as a change to the building. To understand the architecture, the relative scale matters more: the entrance building is low compared with the two towers, yet its interior has several levels and accommodates a wide range of functions.
What challenges had to be addressed when building between the existing buildings?
Construction took place in the narrow gap between existing buildings; according to representatives of the contractor MOST, work in the neighbouring buildings continued throughout. The new structure therefore could not be treated as a freestanding pavilion on an empty site. Engineers had to check how its loads were transferred to the existing parts of the complex and reinforce the foundations. Stroitelnaya Gazeta provides details of work on the load-bearing structures of the four basement levels: concrete was pumped upwards from below under pressure.
The dome’s curved steel arches tilt up to 15 degrees from the vertical. The construction description specifies a tolerance of less than five millimetres for their positioning in three dimensions. These figures explain why visual lightness does not mean ease of installation: several large load-bearing elements had to align with the geometry of the roof and the existing towers precisely enough to support the subsequent layers of the façade.
In entrance building dossier lists 29 steel arches. This number matters when considered alongside the layout: the frame creates a large hall without internal columns, suitable for receptions and meetings. The glazed surface and projecting portals are then assembled on this supporting structure. What appears to be a ‘glass roof’ is therefore more accurately understood as several interconnected engineering layers: the arched frame, glazing units, fixing assemblies and the outer shell of the entrances. Dispensing with columns here supports the intended use of the shared hall, as well as creating a sense of visual lightness.
A parametric digital model was used for the curved elements. The contractors describe the process as a sequence of adjustments to components based on the actual geometry of the preceding layer as installed. The curvature affected joints, fixings, waterproofing, insulation and fire safety requirements. The entrance design therefore required specialist engineers and manufacturers alongside the architects behind the concept.
The curved glass building at Sberbank City in May 2026. Wikimedia Commons, Moscow 2026-05-26 08.jpg, author: Perituss, licence: CC0 source, license
Why do the portals look golden?
The triangular panels at the entrances are made of stainless steel with a champagne-coloured coating. According to material supplied by those involved in the project, grade 316L steel was used for the façades, with the colour achieved through vacuum deposition of titanium nitride. This coating provides both a decorative finish and surface protection. The word ‘golden’, often used in descriptions of the entrance, refers to its visible colour; the cladding should not be understood to be made of gold.
The portal’s surface curves in two directions, so the outer shell was divided into triangles of varying sizes. An analysis by the consortium of Struktura and Makrofabrika gives side lengths of up to 2.5 metres for individual elements. This geometry could be calculated and fabricated in sections, then assembled on the supporting frame.
An analysis by those involved in the construction clarifies the scale of the portal: the canopy projects 11 metres, with a support area just 1.5 metres wide. Sheets measuring 2 × 3.8 m were fabricated for the 316L steel cladding; the champagne-coloured coating was applied separately. These details explain why dividing the surface into triangles was a construction solution, as well as a decorative pattern.
The portals work in tandem with the more restrained glass façade. Materials from the supplier AGC describe the choice of silver reflective glass for the main entrance facing the Third Ring Road: it creates a uniform surface and accentuates the colour of the metal surround. A different product was chosen for the roof, designed to transmit visible light and reduce solar heat gain. The phrase ‘glass entrance’ conceals several technically distinct envelopes, each serving a different purpose.
The glass properties described by AGC relate to the selected material. The supplier’s publication does not include measurements of light levels in each office or temperatures beneath the roof after the building came into use.
The façade glazing also had to meet fire safety requirements. The manufacturer describes the use of fire-resistant glass in parts of the entrance area. Identifying the specific material here serves more than simply listing brands: where the office towers are linked, the transparency of the façade is constrained by engineering requirements, rather than determined solely by the architects’ desire to create a light-filled space.
The glass towers of Sberbank City in Moscow, 9 September 2026. Wikimedia Commons, Sberbank City sep26.jpg, author: Igor3188, licence: CC0 source, license
How were the towers’ new façades matched to the existing glazing?
Parts of the towers’ façades had already been glazed before work resumed. By the time the project continued, the manufacturer of the original glazing was no longer known. An AGC technical publication describes how the company selected a new coating using samples of the old glass to match the colour and reflectivity of the existing and new sections. This case makes continuity in the façade material quite literally visible.
AGC selected a different type of heated insulated glass unit for the sloping upper sections of the towers. This choice reflects the geometry of the cut-off tops and differs from the solution used for the vertical façades.
How is the space beneath the saddle-shaped roof arranged?
Beneath the saddle-shaped roof are entrances to both towers, meeting spaces, a conference area and restaurants. On the lower level, a central reception desk directs people towards the lift lobbies, with a waiting area and café nearby. This gives staff and visitors a shared point of arrival instead of two separate entrances.
Further inside are meeting rooms and a conference area, with a tiered amphitheatre alongside. The OfficeNext project description specifies that the flexible hall accommodates 120 people and can be divided into three smaller rooms. This is no mere decorative addition to the façade: the architects needed to accommodate events and meetings with partners within the same space that serves as the entrance every day.
In Evolution Design’s scheme, restaurants occupy the cantilevered terraces, while living trees, green walls and trailing plants are incorporated into the entrance building. The interior description explains the planned uses of the space but does not specify the current access rules for the venues or office towers.
Dining and social spaces are located above. Evolution Design describes the main restaurant as a ‘Magic Garden’, while the other two spaces, ‘Cherry on Top’ and ‘Chaika’, each have their own interior theme. In the latter, the body of a GAZ Chaika car forms the centrepiece, integrated into the seating area. This detail may seem unexpected, but its purpose is clear: to bring variety to the large shared space and give the different rooms memorable landmarks while maintaining a unified network of connecting routes.
In Evolution Design’s project description, the three restaurants are on the first upper level, with the bar on the level above, directly beneath the glass roof. A broad staircase connects them without taking visitors into the towers’ office corridors. This arrangement explains why the entrance building needed three levels: everyday foot traffic passes through below, while spaces for longer meetings are located above.
The contractor Pridex describes floor slab edges curved in two planes and large-format wall cladding. On the upper level, ventilation ducts were integrated into the parapets and the curved bar counter: the building services had to be adapted to the curving interior.
According to Pridex, underfloor heating and cooling were installed on the third level. The ventilation and climate control systems had to be coordinated with the open-plan layout and the curved bar counter.
How have the towers themselves changed?
The towers’ internal layout was adapted to the needs of a large company. Evolution Design reports designing the interiors of more than 40 floors in each tower, covering around 143,000 square metres in total. Both towers have similarly arranged workspaces, but use different colour schemes and graphics to help people find their way around.
The change in intended use is also evident on the upper levels. A 2008 description of Mirax Plaza earmarked the upper levels of the towers for apartments. In Evolution Design’s description of the completed headquarters these levels house meeting rooms, collaborative workspaces and a floor dedicated to sport. This comparison concerns the intended uses set out in the designs; it does not establish that any completed apartments were actually dismantled: the earlier text described future plans, while the later one described a completed office project.
The upper floors of the Sberbank City towers with illuminated windows and the moon in the dark sky, 18 October 2024. Wikimedia Commons, Sberbank City 01.jpg, author: mos.ru, licence: CC BY 4.0 source, license
Evolution Design created two collaborative workspaces with different purposes: the quiet Chill for focused work and the more open Fun for group discussions. The practice placed a gym on the 40th floor.
In one of the tower’s upper conference rooms, Evolution Design clad a supporting column in Corian and shaped it to resemble a tree. The project description shows how the architects integrated this essential load-bearing structure into a double-height meeting space.
What changed inside the towers’ upper floors?
Evolution Design positioned workstations beside the external glazing, with meeting rooms and rooms for focused work closer to the circulation routes. The towers have similar layouts, but different colour schemes and graphics help people find their way around the more than 80 floors across the two buildings. According to the studio’s description, each floor also has coffee points, drinking water stations, a small exercise area and a space for a short break.
In headquarters project dossier lists a pilot-floor phase in 2019, further design work until June 2020 and implementation until August 2021. This provides a more precise chronology than simply saying that “the complex was built in 2021”. The office layout was first tested and developed, followed by the completion of construction and interior works. The entrance between the towers was designed during an overlapping period.
The office floor area listed in the dossier is 142,360 square metres, while the Evolution Design page rounds it to 143,000. Both figures refer to the interiors of the two towers. They are not the same as the areas of the entire business district, the entrance building or the original Mirax Plaza scheme. Conflating these figures creates the false impression that the sources disagree about the size of the same property, when in fact they are measuring areas with different boundaries.
Was the whole of Sberbank City completed in 2021?
The two headquarters towers and the entrance between them were completed in 2021; the entire business district was not yet finished at that point. The wider Sberbank City development includes other buildings and phases. One example is Building V, which the architectural practice TPO Pride presents as a separate project on its project page, listing its status as under construction.
According to the architectural practice, the building has a wedge-shaped form, a double-skin glazed façade, 17 above-ground and five underground floors, a covered atrium and a grand staircase. Pride and Nikken Sekkei were involved in its design. These features should not be attributed to the glass entrance between the towers: the word ‘atrium’ appears in descriptions of both structures, but they are separate buildings.
On TPO Pride’s page lists the period 2019–2025 for Building V while retaining the note ‘in progress’. This date range in the portfolio does not in itself confirm that the building has been brought into use, while the note reflects the status stated by the architectural practice on the page viewed on 8 November 2026. These details do not establish an exact opening date for the building or justify describing it as part of the entrance between the towers completed in 2021.
What can a view of the complex from outside reveal?
From outside, the main turning point in its history is clearest: the straight-sided towers of the original design and the low glass entrance that connects them. Looking at the space between the towers, you can see how the roof rises towards the portals and dips in the middle. This offers a visible clue to the design challenge: creating enough space for a shared central hub without unnecessarily blocking daylight to the lower floors.
Viewing the exterior also helps distinguish the entrance from neighbouring buildings in the district. Triangular metal panels mark the ends of the new structure, while the towers retain their distinct vertical silhouettes. The façade alone cannot tell you whether all the interior areas are in use or what access restrictions apply, but it does reveal where the architects connected the previously separate buildings.
A Sberbank City tower rising above the Moskva River. View from Shelepikhinsky Bridge, May 2025. Wikimedia Commons, Moscow, view from Shelepikhinsky bridge — Belorussky bridge,Sbercity May 2025 04.jpg, author: Retired electrician, licence: CC0 source, license
The high-rise complex is included on the route the ‘Poklon City’ tour from Poklonnaya Hill to Moscow City. Along this route, you can view the towers and glass entrance from outside and see how they reflect the architectural vision; the tour description does not promise access to the headquarters’ interiors.
Sources
- Sergey Kiselev & Partners: list of projects
- Elevel: previous project names
- Kommersant: Sberbank to relocate its headquarters near Moscow City
- Sber: headquarters wins a Best Office Awards 2022 accolade
- Evolution Design: Entry Building to Sberbank Headquarters
- OfficeNext: entrance to Sberbank’s headquarters
- Evolution Design: Sberbank Headquarters
- TPO Pride: Sberbank City complex
- Radius: Poklon City tour
- Archi.ru: Towers at the Crossroads, the 2008 Mirax Plaza project
- Archi.ru: Moscow Architectural Council on a building in the former Mirax Plaza complex
- Archi.ru: Golden Diadem, the entrance between the towers
- Evolution Design: Sberbank Offices Building E
- Evolution Design: Sberbank Offices Building G
- Archi.ru and AGC: glass for Sberbank City
- Stroitelnaya Gazeta: Sber gets a high-tech connection
- Pridex: the bank’s public space
- OfficeNext: Sberbank headquarters, a 2021 project

We took a tour of Taganka designed for 12-year-old children. It was an excellent programme. We covered a great deal of ground and learnt so much. We discovered the story of Dryanaya Street and discussed the Vladimir Highway, the surrounding monasteries and churches, and the Old Believers. We now know where Korovin was born, where Stanislavsky was born and raised, where the Morozov merchant children lived, and why Arseny Morozov was considered such an outrageous figure in his day. We also discussed Solzhenitsyn, discovered where Stalin Avenue was supposed to be built, saw the bunker, walked to the Russian metochion of the Mount Athos Monastery, and learnt why the Illuzion cinema made Taganka famous. Of course, no tour would have been complete without Vysotsky and Lyubimov. We also touched briefly on Taganka Prison, although naturally we did not go there. All in all, it was an exceptionally rich and informative tour! Our guide Alexander was superb!
Our thanks to our guide Alexander for a magnificent sightseeing tour. Alexander’s love for Moscow and its history, his wide-ranging knowledge, elegant and engaging delivery, and personal charm make the tour not merely interesting and informative, but truly delightful! Thank you, Alexander! Tatiana and Tatiana, St Petersburg
On July 18th, we participated in the "Soul of Moscow" group tour led by Alexander. Kitay-gorod and its surroundings revealed a new side to us, and everyone thoroughly enjoyed it. Some of us began intensively studying related materials to broaden our horizons. We'll be back, and we highly recommend it! You won't regret it.
Good afternoon, on June 23rd we had a tour called " The Soul of Moscow ," led by Alexander. He's a very pleasant young man. We visited such lovely courtyards and alleys with him that we never even knew existed, and we learned so much. We really enjoyed everything, and we hope to continue our acquaintance. Alexander! Thank you! We had a great time with you, and we thoroughly enjoyed it. See you there!
This isn't my first time with Radius. This time, I took the Moscow metro . The goal was not only to admire the underground palaces but also to learn how to navigate the metro. As a resident of a region without a metro, I was a bit apprehensive and didn't understand how to navigate the metro. Of course, the internet helps, but live communication is much better. Tour guide Yulia handled this task perfectly. The information was accessible and interesting, the presentation was calm, and the communication style was very friendly. Thank you very much for the tour and the practical experience.
Good afternoon! I gave the "Soul of Moscow" tour to some of the capital's guests. We were thrilled to hear our guide, Anton. It was so informative and engaging, and very warm. To say we were absolutely delighted is an understatement. It turned out to be a truly family-friendly excursion. We learned so many interesting facts. The material was presented professionally, all our questions were answered, and we saw so much. It was simply WOW! Thank you so much, Anton, he's the best!!!!! From now on, I'll only come to you, the Radius team. I highly recommend it. I promise we'll see each other again soon on other tours.
Overall, the tour left a positive impression! Thanks to Alexander for the walk through the courtyards and atmospheric spots of Kitay-Gorod; we certainly wouldn't have done it on our own. The tour was comfortable, and the guide spoke confidently and calmly. One thing we personally missed: we would have liked more of the historical part, relating to ancient Moscow and the history of Kitay-Gorod. There were quite a few stories about the Soviet period and the bar scene, but for our group, this wasn't particularly relevant. We think the program could be a little more tailored to the age and interests of the group. It would also have been interesting to add more historical facts, monuments, and details about old Moscow and the area itself. That said, the tour was still interesting, and some places and churches were truly memorable. These aren't really "cons," but rather suggestions for an even more comprehensive program.
Hello! We had a corporate group of 10 people. Our guide was Anton, and we had a tour of Bulgakov. I would like to point out the excellent organization; everything went smoothly. The managers were very accommodating to our changes in the number of participants. The bus was very comfortable. Anton is a super-engaged and motivated guide. He lives this history and is delighted to share his knowledge and create an unforgettable experience. Everything went well. I highly recommend it!
Thank you for a fascinating tour! It gave me so much food for thought to explore! Note: Review of the "Zamoskvorechye" tour with guide Maria.
I'd like to express my gratitude on behalf of our team! Thank you for keeping to our scheduled schedule despite our lack of organization. Our colleagues appreciated your preparation for the tour! It was informative. Note: Review of the "Modern Residential Complexes, Factory Past, and Avant-Garde" tour of the ZILART residential complex with guide Maria. Maria prepared and conducted a customized tour for employees of the Samolet Group of Companies development company.
Thank you! You have great talent. Good luck! ☺️ You're a wonderful guide! Thank you again! Note: This is a review of the corporate tour "The Heart of the Capital" with guide Maria.
Thank you for a wonderful day today!!)) Note: review of the excursion "The Soul of Moscow" with guide Maria
On behalf of the whole family, I want to thank you for a very informative and interesting tour! Note: This is a review of the "Palace Dungeons" tour with guide Maria.
Good afternoon! I'd like to express my gratitude and that of my guide for organizing the tour! We were very pleased. We'd like to do it again in October, but on a different route — ZIL. Note: This refers to the tour for Samolet Group developers, led by guide Maria.
Thanks to Alexander for the bar tour of Baumanka ! It was fun, exciting, and we discovered so many new places! Awesome! May we reach new heights!
Good afternoon! I was on a tour of Sukharevskaya Square — we went all the way to Tsvetnoy Boulevard. I didn't expect it to be so interesting! For those wondering whether to go — go for it! It truly became one of my most memorable summer memories!
Anastasia, good morning! Thank you and Masha for yesterday! The speakers are happy. The connection through the headphones was often lost, especially at the checkpoint, but that's just our current situation. You could hear if you were standing close, no more than 1.5 meters away. Colleagues have already asked for your contact information. I'd be happy to share it and look forward to another opportunity to work with you. Special thanks to the Director for the Bureau . Note: " Heart of the Capital " tour for participants of the 2025 Moscow Oncology Forum. Guides: Anastasia and Maria.
We'd like to thank Anton and Alexander for leading the tour! It was fascinating to hear how the Krasnaya Presnya district developed and how Prokhorov's influence on our city's development. It was a pleasant immersion into a quiet, previously unexplored area!
Good afternoon, thank you so much, Anastasia. The " Uncle Gilyai " tour was fantastic. Even though we're Muscovites and know a lot about Moscow, the experience was amazing, so much new and interesting happened. We'll definitely be back.
Thank you for the " Heart of Moscow " and " Khamovniki " tours. Anton, a knowledgeable and passionate Moscow guide, gave me the tour. He's a great storyteller, intelligent, well-read, and captivating. You've truly opened up my Moscow to me! I'll definitely be back next summer to explore Moscow with you. I'll recommend your wonderful tour program to all my friends!
Excursions with the Radius travel agency are always a positive experience if you choose them. We planned a tour of Zamoskvorechye on our next visit. We've worked with our guide, Anton, before. We'll definitely recommend him to everyone we know. The tour is informative, not overloaded with dates, and the information is comprehensive yet easy to understand, as it's presented in a light, narrative manner, not like a history textbook, dry and academic. Thank you for this approach. We'll definitely use the Radius agency again on our next visit to Moscow.
Thank you so much for the tour of Zamoskvorechye . Despite the weather, it was very interesting and informative! Note: this refers to the tour with guide Anton.
A huge thank you to Anastasia. We had a fantastic tour of the Patriki district. We learned so much. Anastasia is a true master of her craft. The tour was captivating, not at all boring, lively and interesting. Everyone was delighted. We were full of new impressions. I definitely recommend it. You won't be disappointed!
We explored the Soul of Moscow with my family and Radius on my birthday. Everyone thoroughly enjoyed the walk! Anton shared so many interesting facts about the capital and its history, taking us into spiritual depths no one else had even suspected. Most of us were either born or longtime Moscow residents who spent a lot of time walking around. It was educational, heartwarming, and unforgettable. 🙂 Overall, this wasn't my first time walking around Moscow with Anton, and each time was a real adventure!